Below is a summary document of the Quality Control Plan implemented at the Mur-Tex Company. We invite you to inquire about the actual quality control manual components. From configuration control to material traceability, Mur-Tex will properly document the manufacturing process of your tank. We are not strangers to source inspector relationships and indeed look forward to such business protocols. |
|||||
DOCUMENT CONTROL |
|||||
As part of the overall quality control planning, the Quality Assurance Manager shall review all specifications and write a summary or Index of Quality Control that will be applicable for each customer, job or project. This will include definition of what standards will apply to the order (i.e. PS-15, ASTM, ASME, RTP-1 or others) as well as any exceptions that may apply. Customer approval of the quality plan is required before manufacturing begins. The Quality Assurance Manager shall review construction drawings to verify that the customer has approved them and to assure that only the latest revision is in use. |
|||||
PROCUREMENT AND MATERIAL CONTROL |
|||||
• Materials purchases shall be documented on a numbered purchase order form and checked by the procurement manager to insure that the purchased material conforms to the job requirements. |
|||||
INSPECTION, TESTING AND VERIFICATION |
|||||
• Routine inspection shall be performed on all work and documented on a Daily Field Log. • In addition to the Daily Field Log, processes and inspection of ASME stamped tanks shall be conducted in accordance with the Mur-Tex Quality Control Manual. Mur-Tex Quality Assurance Manuals are proprietary and not available for distribution. Manuals are available for viewing under the supervision of the Quality Assurance Manager. • Mur-Tex Quality Assurance Manager shall conduct a final inspection. |
|||||
PROCESS CONTROL |
|||||
• Fabrication shall be by procedure and shall be documented on the Daily Field Log. The Quality Assurance Manager shall approve all procedures prior to start of manufacturing. |
|||||
NONCONFORMANCE CONTROL AND CORRECTIVE ACTION |
|||||
• Any nonconformances shall be reported from Quality personnel to the Quality Assurance Manager. |
|||||
TEST EQUIPMENT CALIBRATION |
|||||
• Test instruments shall be calibrated annually or when ever instrument accuracy is questionable. |
|||||
|
|||||
TANK HANDLING AND INSTALLATION |
|||||
• The Mur-Tex document Tank Handling And Installation Instructions is shipped with each finished product and is provided to the customer so as to provide for a safe and mistake-free transfer of ownership of the tank. |
|||||